    • First HS2 trains delayed until 2036 as costs soar to £107 billion | News UK
    • Ireland confirms detention of six citizens by Israel during aid flotilla mission
    • Martin Ney sentenced to life for killing three boys from 1992 to 2001
    • EU rebuffs Italy’s calls for more lenient budget rules amid tensions.
    • Abusers are Misusing Doorbell Cameras and Smart Sunglasses as Weapons | News UK
    • International Rescue Committee launches emergency response to Ebola outbreak in Central Africa
    • EU improves preparedness for quarantine measures six years on.
    • Maldives government recovers bodies of five Italian divers after tragedy
    • Memberships
    • Sign Up
    WTX NewsWTX News
    • Live News
      • US News
      • EU News
      • UK News
      • Politics News
      • Business News
      • Tech News
      • COVID – 19
    • World News
      • Middle East News
      • Europe
        • Italian News
        • Spanish News
      • African News
      • South America
      • North America
      • Asia
    • News Briefing
      • UK News Briefing
      • World News Briefing
      • Live Business News
    • Sports
      • Football News
      • Tennis
      • Woman’s Football
    • My World
      • Climate Change
      • In Review
      • Expose
    • Entertainment
      • Insta Talk
      • Royal Family
      • Gaming News
      • Tv Shows
      • Streaming
    • Lifestyle
      • Fitness
      • Fashion
      • Cooking Recipes
      • Luxury
    • Travel
      • Culture
      • Holidays
    WTX NewsWTX News
    Latest News - UK News

    First HS2 trains delayed until 2036 as costs soar to £107 billion | News UK

    0
    By News Desk on May 19, 2026 UK News
    First HS2 trains delayed until 2036 as costs soar to £107 billion | News UK
    Share
    Facebook Twitter LinkedIn Pinterest Email

    Get you up to speed: First HS2 trains delayed until 2036 as costs soar to £107 billion | News UK

    HS2 DELAY
    Transport Secretary Heidi Alexander announced significant delays and cost increases for the HS2 project, with trains now not expected to depart before 2036.
    HS2 PROJECT UPDATE
    Transport Secretary Heidi Alexander stated in the Commons that the HS2 project will now only see trains departing after 2036, with costs soaring to between £87.7 and £102.7 billion.
    PROJECT DELAY
    Transport Secretary Heidi Alexander announced in the Commons that the HS2 project will not see trains depart before 2036, with costs now estimated between £87.7 and £102.7 billion.

    What we know so far

    The HS2 project is facing yet another delay, with the government confirming that trains will not commence operations before 2036, a setback from the previous estimate of 2033. The high-speed railway, aimed at enhancing connectivity between London and the West Midlands, has been beset by delays and escalating costs.

    Transport Secretary Heidi Alexander addressed Parliament, revealing that the project’s costs have surged, now projected between £87.7 and £102.7 billion. She stated that two-thirds of the increased costs stem from missed works and inefficiencies, while inflation not adequately accounted for by previous Conservative governments has contributed to the overruns.

    Alexander accused former administrations of mismanagement, describing the situation as a “slow motion car crash.” She expressed frustration on behalf of taxpayers, passengers, and those working on the railways, insisting that while cancelling the project is not viable, the current government is committed to getting it “off life support” and “on the road to recovery.” MPs have highlighted the ongoing disruptions faced by communities along the route, including traffic issues and outstanding payments to landowners.

    Read in full

    First HS2 trains won’t leave until 2036 after costs balloon to £107,000,000,000 | News UK

    First HS2 trains delayed until 2036 as costs soar to £107 billion | News UK
    The HS2 project has been marred by issues, and now it faces another delay (Picture: HS2 )

    The HS2 saga continues after the government confirmed that the project will be delayed again while projected costs have increased.

    The high-speed railway has been designed to make rail journeys quicker and smoother between London and destinations in the West Midlands, andoriginally, the North.

    But it has been plagued by delays, cost issues and the scrapping of the nothern leg.

    Transport Secretary Heidi Alexander revealed in the Commons today that trains are not able to depart before 2036, casting aside the earlier estimate of 2033.

    Meanwhile, the costs of the megaproject are reaching eyewatering amounts, with projected estimates now between £87.7 and £102.7 billion.

    Sign up for all of the latest stories

    A chunk of the increased costs, around two thirds, us due to works being missed, underestimates and inefficient deliver, the Transport Secretary said. The rest was due to inflation which wasn’t afactored in regularly enough by previous Conservative governments, she added.

    She hit out at the previous governments, accusing them of wasting taxpayer money.

    A graphics map showing the HS2 route and the cancelled northern leg.
    A map shows the confirmed HS2 route to Birmingham and the cancelled northern leg (Picture: WTX)

    The northern legs to Manchster via Crew, and to Leeds, were axed by the Prime Minister Rishi Sunak.

    Alexander said the previous governments have created a ‘slow motion car crash.’

    ‘If this seems like an obscene increase in time and cost, it is,’ she said, adding that she is ‘angry’ on behalf of taxpayers, passengers and those working on the railways.

    Construction continues on a section of tunnelling along the HS2 railway in Wendover, Britain, May 10, 2026.
    Construction of the Chiltern Tunnel section of HS2 in Wendover, one of the longest tunnels on the high-speed rail route (Picture: Reuters)

    MPs lambasted the project in Commons today, saying their constituents in areas with construction have faced disruption for years, including traffic nightmares due to road closures during construction, while some landowners are still waiting for payments for purchased land.

    Transport Secretary said: ‘Taxpayers, passengers and communities along the route have been let down by years of mismanagement on HS2. 

    ‘I share their anger about the waste and mess, but I am proud that this Government has worked with HS2’s new senior team to get this project off life support and on the road to recovery.  

    ‘We will get the job done but we will also take every opportunity to save time and money in the process, getting a grip on delivery, controlling costs, and stripping out the complexity that’s plagued the project in the past. 

    ‘We can and must build big infrastructure projects in Britain. But we also need competent people in charge of them. This is the same team that delivered the Elizabeth Line. We have done it before, we will do it again.’ 

    Cancelling the entire project is not an option, Alexander suggested.

    She said scrapping the project entirely would cost nearly as much as finishing it.


    Comment now
    Comments

    Add WTX as a Preferred Source on Google
    Add as preferred source

    London UK featured
    Previous ArticleIreland confirms detention of six citizens by Israel during aid flotilla mission

    Keep Reading

    Abusers are Misusing Doorbell Cameras and Smart Sunglasses as Weapons | News UK

    Two Teens ‘Sexually Assaulted on Great Yarmouth Beach’, Manhunt Underway

    London Tube Strikes Confirmed for This Week: What You Should Know

    Woman detained for carrying a ‘genuine sword’ at Unite the Kingdom protest | News UK

    BT Tower in London set for major hotel makeover following £275 million sale

    Metropolitan Police deploy 4,000 officers for rival marches in London

    Add A Comment
    Leave A Reply Cancel Reply

    From our sponsors
    Editors Picks

    Review: Record Shares of Voters Turned Out for 2020 election

    January 11, 2021

    EU: ‘Addiction’ to Social Media Causing Conspiracy Theories

    January 11, 2021

    World’s Most Advanced Oil Rig Commissioned at ONGC Well

    January 11, 2021

    Melbourne: All Refugees Held in Hotel Detention to be Released

    January 11, 2021
    Latest Posts

    Abusers are Misusing Doorbell Cameras and Smart Sunglasses as Weapons | News UK

    May 19, 2026

    Two Teens ‘Sexually Assaulted on Great Yarmouth Beach’, Manhunt Underway

    May 18, 2026

    London Tube Strikes Confirmed for This Week: What You Should Know

    May 18, 2026

    Subscribe to News

    Get the latest news from WTX News Summarised in your inbox; News for busy people.

    My World News

    Advertisement
    Advertisement
    WTX News - Latest Global news and analysis and Breaking news with Exclusive News Briefings
    Facebook X (Twitter) TikTok Instagram

    News

    • World News
    • UK News
    • US News
    • EU News
    • Business
    • Opinions
    • News Briefing
    • Live News

    Company

    • About WTX News
    • Register
    • Advertising
    • Work with us
    • Contact
    • Community
    • GDPR Policy
    • Privacy

    Services

    • Fitness for free
    • Insta Talk
    • How to guides
    • Climate Change
    • In Review
    • Expose
    • NEWS SUMMARY
    • Money Saving Expert

    Subscribe to Updates

    Get the latest creative news from FooBar about art, design and business.

    © 2026 WTX News.
    • Privacy Policy
    • Terms

    Type above and press Enter to search. Press Esc to cancel.